How long will the winning result be announced after the bidding?

Announce the winning result within three days after bidding. According to the law, the tenderer shall publicize the successful candidate within 3 days from the date of receiving the bid evaluation report for the project that must be subject to tender according to law, and the publicity period shall not be less than 3 days. Bidders or other interested parties who have objections to the bid evaluation results of projects that must be subject to tender according to law shall raise them within the publicity period of the successful candidate.

Legal basis: Article 56 of the Regulations for the Implementation of the Bidding Law of People's Republic of China (PRC).

If the business and financial status of the candidate winning the bid has undergone major changes or there are illegal acts, and the tenderer thinks that it may affect his performance ability, it shall be reviewed and confirmed by the original bid evaluation committee in accordance with the standards and methods stipulated in the tender documents before the bid-winning notice is issued.

Article 57

The tenderer and the winning bidder shall sign a written contract in accordance with the provisions of the Bidding Law and these Regulations, and the main terms of the contract, such as the subject matter, price, quality and performance period, shall be consistent with the contents of the bidding documents and the winning bidder's bidding documents. The tenderer and the winning bidder shall not conclude other agreements that deviate from the substantive contents of the contract.

The tenderer shall, within 5 days after signing the written contract at the latest, return the bid bond and the interest on the bank deposit for the same period to the winning bidder and the unsuccessful bidder.

What is the specific process of bidding?

1. Prepare prequalification and bidding documents;

2. Issue a prequalification announcement;

3. Pre-qualification;

4. Selling the bidding documents and answering questions and addenda;

5. Receiving the tender documents;

6. Select bid evaluation experts;

7. Bid opening;

8. Review of bid documents;

9. Calibration;

10, release the bid-winning notice of construction project;

1 1. Contract negotiation and signing before signing.