What happened to more than 40 unfinished buildings left by Kunming's city-building campaign?

In the early years of Kunming, because of the city-building movement, the number of projects increased greatly, and some small and medium-sized real estate developers with weak strength poured in. In the rapid expansion, they encountered various risks such as operation, environmental protection, politics and commerce, which laid the foundation for the large-scale pre-sale of real estate.

According to incomplete statistics, from 20 14 to 20 15, in addition to other happy cities, a number of projects such as Yunxi Jindi, South Asia Gate, Boiling City, Jinheng Fortune Plaza, Yufeng International, Chen Ao Center and Datun City were added to the list of unfinished buildings; During the peak period, there were more than 40 unfinished projects in Kunming market.

In March this year, the Housing and Construction Department of Yunnan Province issued the "Notice on Comprehensively Cleaning up and Renovating Unfinished Buildings", requiring the housing and construction departments of all cities and States to fully understand the base and the real situation before April 30, 2020; Formulate a feasible disposal work plan to ensure that the "unfinished and legacy problems" in the province are all cleared up.

Extended data

The government and developers hope that the owners can "save themselves";

Faced with the unfinished problem of another happy city, the local government has tried similar efforts. On August 3 1, 2065438, the Kunming municipal government replied to the owner's question on the message board of People's Daily, saying, "The developer Xiaoan Company cooperated with Poly Real Estate to develop plots 6 and 7, and took some funds ... The district government requires enterprises to set up special fund accounts, which will be supervised by the District Urban Reform Bureau to urge enterprises to collect all funds for the project closing work. "

At that time, the Urban Renewal and Reconstruction Bureau of Guandu District of Kunming also said in the relevant reply: "Recently, Cinda Company and Poly Company intend to cooperate with Xiaoan Company to develop the project. After the cooperation, the problems existing in plots 4 and 5 of the project and the follow-up problems of the whole project will be solved. "

In the process of the government looking for the receiver, the owner of No.5 plot in Biexing Happiness City embarked on the road of self-help. According to earlier media reports, the delivery time of plot 5 was 20 15 12, but it has been suspended since it was capped. From 20 15 to 20 18, the owners raised funds for self-help many times, and finally another plot of No.5 in Happiness City barely met the occupancy conditions, and some owners were able to hand over the house for occupancy. Some commentators said that the No.5 plot of Biexing Happiness City was the first typical case of owner-help uncompleted residential flats in Kunming.

China Net-There are more than 40 unfinished buildings in Kunming, and the government and developers hope that the owners will "save themselves".